Annual fee of €15,000 per MW and coverage of at least 60% of consumption from new renewable energy sources for data centres, under a bill from the Ministry of Environment and Energy submitted to Parliament.
The charge is calculated on the maximum consumption capacity and is payable from the start of the facility's operation, in favour of household consumers and the municipalities of the area. Thus, for a data centre with a capacity of 100 MW, the annual fee would reach €1.5 million. Data centres that already operate and have been connected to the grid are exempt from the new rules.
To cover 60% of annual consumption, Renewable Energy Source (RES) stations must be located in the Greek interconnected system and must not have received an operating licence or, where applicable, a grid connection certificate when the data centre's connection request was submitted. They must also hold a Final Connection Offer when bilateral electricity purchase agreements are submitted. If the required RES stations and storage systems are not operating by the time the data centre is connected to the grid, its connection will be suspended.
To connect to the electricity grid, the investor must, as a general rule, submit a complete Environmental Impact Study file, a pre-approval of the building permit and evidence of the right to use the land. The required guarantee letter amounts to €200,000 per MW, or €20 million for a 100 MW project.
Investments connected to the Transmission System face an additional criterion: annual turnover must exceed 30% of the presumed construction cost, which is estimated at €10 million per MW. Projects above 200 MW will be examined first, provided they are accompanied by the development of new distributed generation or storage capacity with a nominal power of at least 80% of the maximum consumption capacity.
The original draft for public consultation provided neither for an annual fee nor required that green energy come from new RES stations in Greece. The text submitted to Parliament also prohibits operating aid for the part of the capacity of energy projects that covers these obligations. However, the 60% threshold can be reduced by ministerial decision, provided the agreements concern RES of a technology other than photovoltaics, or RES stations combined with storage.
Investors that already hold a connection offer or contract will have more time to adapt, as the deadline is extended from five to twelve months. The period for accepting a new connection offer is also increased from two to three months. Subject to conditions, the distribution operator HEDNO will be able to grant instalment-based offers for facilities with a total capacity of up to 40 MW. In areas without the required urban planning schemes, the pre-approval of the building permit may be submitted at a later stage.